Expansion Update - April 21, 2025

Expansion Update - April 21, 2025

Tower 3rd and 4th floors

  • Installation of additional med gases on bed headwalls are almost finalized
  • Stairwell rubber treads are installed
  • IT installation on all floors is underway, starting on 4th and working down

Tower 2nd floor

  • There were some set-backs with the operating room suite, sterile processing, and central supply equipment installation, but work should be wrapping up soon
  • ICU rooms are complete with cabinetry and countertops
  • Emergency fire doors and sprinklers are being installed in the transition hallways between the existing building and the new tower; flooring will be next

Tower 1st floor

  • Ceiling tile, drywall, insulation, electrical, plumbing, lighting, and HVAC duct work are nearing completion
  • Flooring install has begun on the north and south ends with installation in the main mall area scheduled to be last

Other Hospital Renovations

  • Front canopy work continues with capstone installation, and a painted purple accent strip will be coming soon
  • Sidewalks and parking lots are complete
  • Light pole installation continues and electricity for working lights is expected this week
  • Landscaping has begun
  • The new patient registration area at the front entrance is making progress with plumbing, mechanical, HVAC and electrical installations
  • Glass for the front doors and patient registration area partitions have been ordered

Anticipated tower move-in date: mid-to-late June.

 