3rd and 4th floors

  • Patient room cabinets and nurse work station cabinets are installed
  • Laminate flooring inside patient rooms and hallways are almost complete
  • Nursing station desk tile work is being installed
  • Decorative wall protectors are going up in hallways and installation of bed rails will follow
  • Ceiling tile in elevator lobbies has been installed
  • Nurse work area cabinets and flooring is complete

2nd floor

  • ICU rooms are drywalled
  • A/C and heat will be turned on soon, then flooring work can begin
  • Transition hallway from new tower to existing area near ICU has been opened

1st floor

  • Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues

Other

  • New patient registration area by front entrance is framed, and drywall and HVAC/electrical installations are underway
  • Front entrance canopy framing and stonework preparation continues
  • Front driveway is poured, and concrete pours for sidewalks and parking area are next
  • Side entrance and service entrance concrete areas are poured
  • Wall to hide service entrance is complete, and bollards to protect equipment/walls/building are installed

 

Projected Move-in Date – March 2025

 