Expansion update - February 24, 2025

Expansion update - February 24, 2025

Tower 3rd and 4th floors

  • Finishes are going in, such as bathroom mirrors, light switch plates, soap dispensers, paper towel holders, and cabinet shelving to raise trash can to proper height
  • Fire alarm installation has begun
  • Patient room and waiting room furniture is arriving

Tower 2nd floor

  • Operating room suites are nearing completion with overhead lighting, cabinetry and equipment install beginning this week
  • Flooring installation continues in ICU patient rooms
  • Caulking and painting is underway
  • Steel column blocking a rear hallway entrance was moved
  • Transition hall connecting the tower to the existing building is being leveled in preparation for walls and flooring

Tower 1st floor

  • Glass doors installed on side entry doors
  • Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues

Other Hospital Renovations

  • Front canopy work continues with brick and capstones
  • New patient registration area by front entrance is drywalled, floor has been leveled, and plumbing, mechanical, HVAC and electrical installations continue
  • Work to prepare temporary endoscopy area continues
  • New exterior lighted sign install is complete.

 