Tower 3rd and 4th floors
- Finishes are going in, such as bathroom mirrors, light switch plates, soap dispensers, paper towel holders, and cabinet shelving to raise trash can to proper height
- Fire alarm installation has begun
- Patient room and waiting room furniture is arriving
Tower 2nd floor
- Operating room suites are nearing completion with overhead lighting, cabinetry and equipment install beginning this week
- Flooring installation continues in ICU patient rooms
- Caulking and painting is underway
- Steel column blocking a rear hallway entrance was moved
- Transition hall connecting the tower to the existing building is being leveled in preparation for walls and flooring
Tower 1st floor
- Glass doors installed on side entry doors
- Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
Other Hospital Renovations
- Front canopy work continues with brick and capstones
- New patient registration area by front entrance is drywalled, floor has been leveled, and plumbing, mechanical, HVAC and electrical installations continue
- Work to prepare temporary endoscopy area continues
- New exterior lighted sign install is complete.