It’s been almost a year since our expansion project for an updated facility focused on patient-centered care began. Construction of the 4-story patient tower is at the half-way point. Weather permitting, the new tower is scheduled open in December 2024.
- 3 A/C chillers are installed.
- Elevator shafts and stairwells have been painted with a special waterproofing paint (yellow).
- Strapping for HVAC ducts, temporary lighting, and plumbing pipe supports are installed.
- Installation of HVAC ducts has begun on the 4th
- Plumbing rough ins and framing for walls has started on the 4th
- Plumbing rough ins and framing for walls has started on the 4th
- Window frames have arrived and scaffolding to install is going up.
- The 2 “crosses” seen on top of the building are anchors for a window washer to attach equipment.