Expansion Update - January 28, 2025

Expansion Update - January 28, 2025

3rd and 4th floors

  • Patient room head walls, foot walls, cabinets, nurse work stations , and plumbing fixtures are installed
  • Laminate flooring inside patient rooms and hallways are complete
  • Bed rail installation is complete

2nd floor

  • Operating room suites are near completion with cabinetry install to begin soon
  • A/C and heat is turned on
  • Flooring work has begun
  • Work in the temporary endoscopy area continues

1st floor

  • Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
  • Transition hallway from new tower to existing area near the cath lab is underway
  • All four elevators are complete and functional

Other

  • New patient registration area by front entrance is drywalled and plumbing, mechanical, HVAC and electrical installations are ongoing
  • Front entrance canopy framing and stonework preparation continues; new glass doors will be installed in the next few weeks
  • Final front driveway/parking area pour and concrete pour for sidewalks are complete
  • Exterior details on the tower are nearing completion

Projected tower move-in, and opening of front entrance and new registration area, is expected to be mid-April.

 

connecting hallway on 1  patient room nurse area  registration area 3  crash rail in hallway 2  

concrete parking lot 5  elevator 1&2  front canopy side view3  

surgery nurses stations  operating suite

 patient room footwall  patient room bathroom  

patient room headwall