Expansion Update - March 17, 2025

Expansion Update - March 17, 2025

Tower 3rd and 4th floors

  • Patient room and waiting room furniture is arriving
  • Finish installs continue, such as soap dispensers and paper towel holders

Tower 2nd floor

  • Operating room suite, sterile processing, and central supply equipment is being installed
  • ICU rooms are nearing completion

Tower 1st floor

  • Ceiling tile, drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
  • Stairwell rubber treads are being installed

Other Hospital Renovations

  • Front canopy work continues with capstone installation, sidewalks, and dirt grading preparations for landscaping
  • New patient registration by front entrance is making progress with plumbing, mechanical, HVAC and electrical installations
  • Work to prepare temporary endoscopy area continues

Picture1-Mar-21-2025-04-43-48-5475-PM  Picture2-Mar-21-2025-04-43-48-9127-PM  Picture3-Mar-21-2025-04-43-48-3085-PM  

Picture4-Mar-21-2025-04-43-49-4522-PM  Picture5-Mar-21-2025-04-43-47-5989-PM  Picture6-Mar-21-2025-04-43-49-7702-PM  Picture7-4

Picture8-4  Picture9-3  Picture10-3