Expansion Update: November 18, 2024

Expansion Update: November 18, 2024

3rd and 4th floors

  • Bathroom epoxy flooring is being poured, and tile and fixtures are being installed.
  • Laminate bed walls are going up
  • Nursing work stations and room cabinets are being fitted inside patient rooms
  • Nursing station desks are being installed 

2nd floor

  • The OR suites are taking shape with hand washing station / viewing window installations and ceiling installation
  • The new ICU rooms are drywalled in 

 

1st floor

  • Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues 
  • Elevators 1&2 are operational, elevators 3&4 are being installed

 

Other

  • Front entrance canopy framing continues
  • Front parking areas are moving forward with new concrete pours
  • The A/C tie-in between the new tower and existing building is complete 
  • Final exterior stonework is being installed.

 

New Projected Move-in Date – March 2025

image002-4   image003-2  image004-1   image010

image005-1  image006-1   image007-1

image009   image008-1