3rd and 4th floors
- Bathroom epoxy flooring is being poured, and tile and fixtures are being installed.
- Laminate bed walls are going up
- Nursing work stations and room cabinets are being fitted inside patient rooms
- Nursing station desks are being installed
2nd floor
- The OR suites are taking shape with hand washing station / viewing window installations and ceiling installation
- The new ICU rooms are drywalled in
1st floor
- Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
- Elevators 1&2 are operational, elevators 3&4 are being installed
Other
- Front entrance canopy framing continues
- Front parking areas are moving forward with new concrete pours
- The A/C tie-in between the new tower and existing building is complete
- Final exterior stonework is being installed.
New Projected Move-in Date – March 2025