Expansion Update - September 27, 2024

Expansion Update - September 27, 2024

3rd and 4th floors

  • Bathroom tile and fixtures are being installed.  Once the A/C is connected, they will begin pouring the epoxy flooring. 
  • Laminate bed walls are going up
  • Nursing work stations are being fitted inside patient rooms

1st and 2nd floors

  • Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
  • The OR suites are taking shape with revised electrical outlet placements and hand washing stations/viewing window installations

Other

  • Installation of elevators 3 & 4 has begun.  Elevators 1& 2 are on hold because of missing parts.
  • Front parking areas are moving forward with new concrete pours
  • Concrete footings for the new front canopy supports are underway
  • Preparations for the A/C tie-in between the new tower and existing building are being made 
  • The majority of the exterior stonework and windows are in place.

New Projected Move-in Date – March 2025

NOTE: A staff walk-thru will be planned once the elevators are installed and A/C is turned on. 

 