3rd and 4th floors
- Bathroom tile and fixtures are being installed. Once the A/C is connected, they will begin pouring the epoxy flooring.
- Laminate bed walls are going up
- Nursing work stations are being fitted inside patient rooms
1st and 2nd floors
- Drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
- The OR suites are taking shape with revised electrical outlet placements and hand washing stations/viewing window installations
Other
- Installation of elevators 3 & 4 has begun. Elevators 1& 2 are on hold because of missing parts.
- Front parking areas are moving forward with new concrete pours
- Concrete footings for the new front canopy supports are underway
- Preparations for the A/C tie-in between the new tower and existing building are being made
- The majority of the exterior stonework and windows are in place.
New Projected Move-in Date – March 2025
NOTE: A staff walk-thru will be planned once the elevators are installed and A/C is turned on.